Kolkata: The
Vivekananda flyover bridge that collapsed on March 31 is one of many examples
of the lack of work ethic of I Venku Reddy Construction Ltd (IVRCL), proving
that actions could have taken to avoid the disaster that killed 27 people and
injured 80 others.
Founded in 1987 by
Indukuri Syam Prasad Reddy, IVRCL, based in Hyderabad’s Banjara Hills, has
completed over 100 projects, but has a record known more for delays and missing
deadlines. IVRCL’s area of expertise is laying pipelines and constructing
irrigation canals, though it has executed highway projects and built bridges
too.
On July 28, 2009, two
laborers involved in laying a drainage pipeline on the outskirts of Hyderabad
were buried alive when a mud wall collapsed. The company had declined to take
responsibility, blaming loose soil for the collapse. After protests, IVRCL paid
compensation, but escaped punishment.
Another project
assigned to IVRCL by the undivided Andhra Pradesh government was a contract to
build 120 flats for MLAs at Hyderguda, in August 2012. The project was to be
completed in 16 months, but as of March 31, 2016, it is only 60 per cent complete.
In Jharkhand, IVRCL was
blacklisted twice, after failing to fulfill two government contracts. The first
pertained to rural electrification in three districts in 2006, where the work
fell far behind schedule and wasn’t satisfactory.
The construction for
Vivekananda flyover bridge was contracted in 2008, and the construction began
in 2009. Since then, it has missed its deadline nine times, with the first
deadline being on August, 2010.
On Friday, two
officials including a chief engineer of the Kolkata Metropolitan Development
Authority (KMDA), which was responsible for supervising work at the Vivekananda
flyover, were suspended. A sub-contractor to whom IVRCL had given some parts of
the flyover work is also being investigated. The company has denied any
compromise with quality of work, or a design defect.
Forensic teams that
collected samples of construction material from the site have identified pillar
no. 40 as the point of the collapse. About 60 pillars of the flyover had been
constructed, and cracks were reported on the girder of this pillar, standing at
the crossing of Chitpur Road and Ganesh Talkies.
No comments:
Post a Comment